Explosion proof | FAQ
 |
Opening an EEx-e junction/terminal box
|
Question:
Can I open an EEx-e junction/terminal box during service
and perform any work there?
Answer:
No! This is absolutely prohibited.
Solution:
Make sure that the circuit(s) have been isolated (switched
off), only then can you start work inside the terminal box.
Take care that only approved tools for Ex areas are being
used.
|
|
back to FAQ overview |
| |
|
|
 |
|
Products for zone 1, 2, 21, 22 (Example ExMax)
Products for zone 2, 22 (Example RedMax)
Products for safe area (Example InMax)
|